Solis_Manual_RHI-1P(5-10)K-HV_USA_V1,1
5. Operation 5. Operation
After setting the language, press "ESC" to access the main page.
Figure 5.3 Main Page
Solar Power: When solar power is generated an arrow ,
indicates the direction of the power flow, and the value is shown
above the arrow.
Battery: When the battery is connected successfully, it will
display “COM OK” and the battery SOC arrow and flow will be
shown. If the battery is not connected it will show “COM FAIL”.
Loads: Loads connected to the AC Grid port that will shutdown in
the event of a grid outage.
KWH
2. 52 6
Smart Meter: When the smart meter is connected successfully,
it will display "RS485 OK", otherwise "RS485 Fail".
Critical Loads: Loads connected to the AC backup port which will
be supported by battery and solar during a grid outage.
Grid: The arrow and value indicate the export/import power of
the hybrid system.
On the main page,
Press "ESC" : View the yield data on monthly bar charts. Then use "UP" and "DOWN"
to change the date and "ENT" to move the cursor.
Press "UP" or "DOWN": View different status on the top left of the main page.
Press "ENT": Enter the main menu.
KWH
2.5 26
COM OK
5.2 Main Menu
There are four submenus in the Main Menu:
1. Information 2. Settings 3. Advanced Information 4. Advanced Settings
Figure 5.4 Main Menu
Settings
Menu
2015-02-23 19 35
Information
Settings
Advanced Information
Advanced Settings
5.3 Information
In the information section, operating data and information data can be viewed.
Sub-sections include:
1.General Info 2.System Info 3.Energy Records 4.BMS Info 5.Meter Info
The example displays are shown in the following figures.
Values are for reference only.
SettingsInformation
2015-02-23 19 35
General Info
System Info
Energy Records
BMS Info
Meter Info
Figure 5.5 Information