User's Manual
Confidential & Proprietary 20/30 SC-DAS
Figure 3.3 – ROU installation diagram side by side
For connecting cables between MRU and ARU conveniently, MRU should install on left side of ARU.
Type2 : 2Layer installation
In case of the narrow space to not install MRU and ARU side by side, we can install RUs into 2layer
To install into 2layer, it need baracket for 2layer installation
First, after installing MRU on the wall and then install the bracket for 2layer installation on the MRU
Second, on top of the installed bracket, install ARU
Completed installation diagram is as follows
Figure 3.4 – ROU installation procedure for 2layer