Installation manual
26
Safety, Installation, and Operations Manual
© Solaria Corporation All rights reserved. Contents subject to change without notice 8-26-19
Power Unlocked by Design
Step 8: Connect the Microinverters as the AC Modules are Installed
A. Place the modules on the roof. Do not place the modules in such a way that places pressure on the microinverter.
Minimum distance from the top edge of the module to the rail should be about 12 inches.
B. As each module is installed, connect the Q Cable to the microinverter. Listen for a click as the connectors engage.
C. Do not allow the rail to press on the microinverter.
Step 9: Manage the Cabling
A. Use cable clips to attach the cable to the module frame. Leave no more than 1.8 m (six feet) between cable clips.
B. Dress any excess cabling in loops so that it does not contact the roof. Do not form loops smaller than
12 cm (4¾ “) in diameter.
WARNING: Tripping Hazard. Loose cables can become a tripping hazard. Dress the
Enphase Q Cable to minimize this potential.
NOTE: Some modules do not include framing on their shortest side. Cable clips cannot attach
to the frameless side for cable management. Plan to use the longer, framed side for cable
management when this is the case.
Cable Clip