Installation Guide

Recommended Versi-Tab Installation Techniques
Staple Tab
Lap Tab
Draw the edge of the two adjoining rolls of
Solarguard together and place the 4" tab
directly adjacent to the 2” tab. You may
want to apply a few staples on 18" to 24"
centers to keep the joined tabs in position. Lay each roll in place with the 4” tab at the leading edge.
As the next roll is placed, lift the 4” tab and slide the 2”
tab from the new roll just beneath the previously-placed
roll as shown above. When installation is complete, the
2" tab should be visible from the building interior and the
4" tab is above, facing the roof.
Fold the top half of the 4” tab over the 2” tab and
staple 6” on center.
To complete the tab seal, fold tabs in half again
and staple again 6” on center, between the
previously-applied staples.