Installation Guide
The following table describes production percentage of AC information by LED color
and ON/OFF/P switch position.
Indication
ON/
OFF/ P
switch
position
LEDcolor
Comment
Red Green Blue
Percentage of AC
Production:
0 - 33 %
ON (1)
OFF ON OFF
This indicates
power
production as
percentage of
rated peak AC
output power
Percentage of AC
Production:
33 - 66 %
OFF OFF ON
Percentage of AC
Production:
66 - 100 %
OFF ON ON
Connection Unit Interface
The Connection Unit is part of the Primary Unit.
NOTE
In the following figure, the connections to the Secondary Unit are shown only
on the left side of the Connection Unit; for an inverter that has two Secondary
Units, similar connections are located on the other side of the unit as well.
Figure 13: Connection Unit bottom and side interface
Safety switch: a manually operated safety switch for disconnecting the DC
power of the SolarEdge system.
Chapter 3: Installing the Primary and Secondary Unit(s) 33
Three Phase Inverter with Synergy Technology Installation MAN-01-00401-1.5