Appendix B - System Behavior Example
34
Appendix B - System Behavior Example
In this example the StorEdge system uses maximize self-consumption mode with zero export limit. The inverter is connected to
L1 and L2 in a split phase home. It supplies loads connected to L1 and to L2 load and exports excess PV power to the grid.
The produced PV power is 2kW, and there is 2kW load on L1 and a 1kW load on L2. The StorEdge system supplies 3kW to the
loads including 1kW from the battery - and exports 0kW to the grid.
The meter measures 4.16A on L1 to the grid and senses 120VAC with positive phase between L1 and Neutral, therefore the
power import on L1 is 4.16A x 120V = 0.5kW. On L2 the meter measures also 4.16A from the grid and senses 120VAC with
negative phase between L2 and Neutral, therefore the power export on L2 is 4.16A x 120V = 0.5kW. Total export power is 0.5kW
- 0.5kW = 0kW. Due to the load imbalance between L1 and L2 there is an 8.33A current on the neutral wire between the home
and utility transformer.
Figure 29: Power Production Flow