Install Manual
Table Of Contents
- Disclaimers
- Support and Contact Information
- Revision History
- HANDLING AND SAFETY INSTRUCTIONS
- IMPORTANT SAFETY INSTRUCTIONS
- Chapter 1: Introducing the SolarEdge Power Harvesting System
- Chapter 2: Installing the Power Optimisers
- Chapter 3: Installing the Inverter
- Chapter 4: Connecting the AC and the Strings to the Safety Switch
- Chapter 5: Activating, Commissioning and Configuring the System Using the Inverter SetApp
- Chapter 6: Setting Up Communication
- Appendix A: Errors and Troubleshooting
- Appendix B: Mechanical Specifications
- Appendix C: External Fan Maintenance and Replacement
- Appendix D: Replacing and Adding System Components
- Technical Specifications - Three Phase Inverters (North America)
Removing the Inverter Cover
Iftheinvertercoverisnotalreadyremoved,usethefollowingprocedureforcoverremoval.
To remove the inverter cover
1. TurntheinverterON/OFF/PswitchtoOFF.Wait5minutesforthecapacitorstodischarge.
2. TurntheSafetySwitchtoOFF.
3. DisconnecttheACtotheinverterbyturningOFFthecircuitbreakersonthedistributionpanel.
4. OpentheAllenscrewsoftheinvertercoverandcarefullypullthecoverhorizontallybeforelowering
it.
CAUTION!
When removing the inverter cover, make sure not to damage the internal components. SolarEdge will
not be held responsible for any components damaged as a result of incautious cover removal.
ATTENTION!
Lors du retrait du couvercle, assurez-vous de ne pas endommager les composants internes. SolarEdge
ne peut être tenue pour responsable des composants endommagés à la suite d'une imprudence dans le
retrait du couvercle.
Creating an Ethernet (LAN) Connection
ThiscommunicationoptionenablesusinganEthernetconnectiontoconnecttheinvertertothe
monitoringplatformthroughaLAN.
Ethernetcablespecifications:
l Cabletype–ashieldedEthernetcable(Cat5/5ESTP)maybeused
l Maximumdistancebetweentheinverterandtherouter–100m/330ft.
NOTE
If using a cable longer than 10 m / 33 ft in areas where there is a risk of induced
voltage surges by lightning, it is recommend to use external surge protection
devices.
For details refer to: https://www.solaredge.com/sites/default/files/overvoltage_
surge_protection_na.pdf.
Figure 29: Example of Ethernet connection
-Three Phase System Installation Guide MAN-01-00527-1.1
54
Removing the Inverter Cover