Install Manual
Table Of Contents
- Disclaimers
- Support and Contact Information
- Revision History
- HANDLING AND SAFETY INSTRUCTIONS
- IMPORTANT SAFETY INSTRUCTIONS
- Chapter 1: Introducing the SolarEdge Power Harvesting System
- Chapter 2: Installing the Power Optimisers
- Chapter 3: Installing the Inverter
- Chapter 4: Connecting the AC and the Strings to the Safety Switch
- Chapter 5: Activating, Commissioning and Configuring the System Using the Inverter SetApp
- Chapter 6: Setting Up Communication
- Appendix A: Errors and Troubleshooting
- Appendix B: Mechanical Specifications
- Appendix C: External Fan Maintenance and Replacement
- Appendix D: Replacing and Adding System Components
- Technical Specifications - Three Phase Inverters (North America)
Figure 25: DC Spring-clamp terminal example - 9kW, 10kW and 20kW inverters
l Forthreephaseinverters14.4kWand33.3kW–ConnecttheDCwiresfromthePVinstallationtothe
DC+andDC-terminalblocks:
a. Insertthescrewdriverintothefrontopeningandrotateitcounterclockwisetoactivatethe
clampmechanism.Thesidelatchholdstheclampintheopenposition.
b. Insertthewireintothesideopeningasdeepaspossible.
c. Slightlyrotatethescrewdrivercounter-clockwisetoreleasethelatch.
d. Removethescrewdriver–thewireissafelyclamped.
Figure 26: DC Spring-clamp terminal – 14.4kW and 33.3kW inverters
5. ClosetheSafetySwitchcover:Attachtheswitchcoverandsecureitbytighteningthefourscrews
withatorqueof1.2N*m/0.9ft.*lb.
6. Ensureproperconduitsealing;inspecttheentireconduitrunandusestandardconduitsealantsto
avoidwaterpenetration.
-Three Phase System Installation Guide MAN-01-00527-1.1
40
Connecting the Strings to the Safety Switch