Install Manual

Table Of Contents
To connect the AC grid to the Safety Switch 9kW, 10kW, 20kW:
1. Strip0516''(8mm)oftheACwireinsulation.
2.
InserttheACconduitintotheAC-sidedrillguidethatwasopened.
NOTE
Connect the equipment grounding before connecting the AC wires to the AC.
Veillez à relier le conducteur de PE (la terre) avant de connecter les fils CA au bornier CA.
3.
Connectthewiresasfollows:
a. Useastandardflat-bladescrewdrivertoconnectthewirestothespring-clampterminals(See
Figure24).
b. Thescrewdriverbladeshouldfitfreelyintheterminalopening.Toolargeabladecancrackthe
plastichousing.
c. Insertthescrewdriver,pressthereleasemechanismandopentheclamp.
d.
Insertthewireintotheroundopeningandremovethescrewdriver–thewireisautomatically
clamped.
Figure 24: AC Spring-clamp terminal 9kW, 10kW, 20kW inverter
-Three Phase System Installation Guide MAN-01-00527-1.1
38
Connecting the AC Grid to the Safety Switch