Install Manual
Table Of Contents
- Disclaimers
- Support and Contact Information
- Revision History
- HANDLING AND SAFETY INSTRUCTIONS
- IMPORTANT SAFETY INSTRUCTIONS
- Chapter 1: Introducing the SolarEdge Power Harvesting System
- Chapter 2: Installing the Power Optimisers
- Chapter 3: Installing the Inverter
- Chapter 4: Connecting the AC and the Strings to the Safety Switch
- Chapter 5: Activating, Commissioning and Configuring the System Using the Inverter SetApp
- Chapter 6: Setting Up Communication
- Appendix A: Errors and Troubleshooting
- Appendix B: Mechanical Specifications
- Appendix C: External Fan Maintenance and Replacement
- Appendix D: Replacing and Adding System Components
- Technical Specifications - Three Phase Inverters (North America)
To connect the AC grid to the Safety Switch – 14.4 & 33.3kW inverters:
1. Removethespring-clampterminalinstructionsfrominsidetheswitch.
2. Strip1⅜''(35mm)oftheACwireinsulation.
3.
InserttheACconduitintotheAC-sidedrillguidethatwasopened.
NOTE
Connect the equipment grounding before connecting the AC wires to the AC terminal block.
Veillez à relier le conducteur de PE (la terre) avant de connecter les fils CA au bornier CA.
4. Connectthewirestotheappropriateterminalblocksaccordingtothelabelsontheterminalblocks
(N,L1,L2,L3).
5.
Usea13/64"(5mm)straightflat-bladescrewdrivertoconnectthewirestotheterminals:
a. Insertthescrewdriverintothefrontopeningandrotateitcounterclockwisetoactivatethe
clampmechanism.Thesidelatchholdstheclampintheopenposition.
b. Insertthewireintothesideopeningasdeepaspossible.
c. Slightlyrotatethescrewdrivercounter-clockwisetoreleasethelatch.
d. Removethescrewdriver–thewireissafelyclamped.
Figure 23: AC Spring-clamp terminal example - 33.3KW inverter
6. Verifythattherearenounconnectedwires.