Installation Guide
NOTE
You can use the activation code that appears on the certification inverter
label to activate the inverter in case of a script error or a missing activation
card.
4. Verify that the inverter is configured to the proper country: Press the up or down
buttons until reaching the ID status screen:
D S P 1 / 2 : 1 . 0 2 1 0 / 1 . 0 0 3 4
5. If required, perform any additional connections before closing the inverter cover
(for example: Communication options connection – refer to
Setting Up
Communication
on page 70
6. Close the inverter cover by tightening the screws with a torque of 3.0 N*m/ 2.2 lb*ft.
7.
Turn ON the Safety Switch. If an additional external DC switch is installed between
the power optimizers and the inverter(s) then turn it ON.
A status screen similar to the following appears on the LCD panel:
V a c [ V ] V d c [ V ] P a c [ w ]
2 4 0 . 7 1 4 . 1 0 . 0
P _ O K : 0 0 0 / 0 0 0 < S _ O K >
- - - - - - - - - - - - - - - O F F
8. Verify that the following information appears on the LCD panel:
P_OK: Appears only upon pairing process completion and first telemetry
reception from the power optimizers. Indicates connection to the power
optimizers and that at least one power optimizer is sending monitoring data.
000/000: Appears only upon first telemetry reception from the power
optimizers. Indicates the number of power optimizers that have been paired
to this inverter.
S_OK: the connection to the SolarEdge monitoring platform is successful
(should appear only if the inverter is connected to the server). If S_OK is not
displayed and the inverter is connected to the server, refer to
Errors and
Troubleshooting
on page 81.
Vac [V]: the grid AC output voltage. Verify the correct value.
Vdc [V]: The DC input voltage of the longest string connected to the
inverter. There should be a safety voltage of 1V for each power optimizer in
the string.
EV Charging Single Phase Inverter Guide MAN-01-00404-1.2
42 Step 1: Activating the System