Installation Guide

CAUTION!
Ensure that the Plus (+) wire is connected to the + terminal and that the Minus
(-) wire is connected to the Minus (-) terminal connector.
ATTENTION!
Veillez à ce que le câble Plus (+) soit connecau terminal + et que le câble -
soit connec au connecteur terminal.
NOTE
For systems with four PV strings per unit or more, fuses
may need to be installed in both the positive and negative
conductors as required by NEC Article 690.9. For more
information, refer to the String Fusing Requirements
in SolarEdge Systems” technical note at
http://www.solaredge.com/files/pdfs/string_fusing_requirements.pdf.
NOTE
SolarEdge's fixed input voltage architecture enables the parallel strings to be of
different lengths. Therefore, they do not need to have the same number of
power optimizers, as long as the length of each string is within the permitted
range.
Figure 21: DC Spring-clamp terminals
5. Close the Connection Unit cover: Attach the switch cover and secure it by
tightening the four screws with a torque of 1.2 N*m/ 0.9 lb*ft.
6. Ensure proper conduit sealing; inspect the entire conduit run and use standard
conduit sealants to avoid water penetration.
EV Charging Single Phase Inverter Guide MAN-01-00404-1.2
40 Connecting the Strings to the Connection Unit