Installation Guide

Installation Procedure
The following is the procedure for installing and setting up a new SolarEdge site. Many
of these also apply to modification of an existing site.
1. Connecting Power Optimizers in Strings, page 27.
2. Recording power optimizer serial numbers (optional), page 46.
3. Mounting the inverter, Page 33.
4. Connecting the AC and the Strings to the Connection Unit, page38.
5. Commissioning and activating the installation, page 41.
6. Connecting the inverter to the monitoring platform, page 47.
7. Configuring the inverter, page 49.
8. Installing the EVCharger Cable - Refer to the installation guide supplied with the
product. The cable and holder can be installed at the same time as the inverter or
added at a later time.
9. Configuring the EV Charger - Refer to the installation guide supplied with the EV
Charger Cable. Configuration can be done only after the EVCharger Cable is
connected to the inverter and the inverter is connected to the monitoring platform. 
Installation Equipment List
Standard tools can be used during the installation of the SolarEdge system. The
following is a recommendation of the equipment needed for installation:
Allen screwdriver for 3mm screw type for the inverter cover, side screws, and
Safety Switch cover.
Standard flat-head screwdrivers set
Non-contact voltage detector
Cordless drill (with a torque clutch)or screwdriver and bits suitable for the
surface on which the inverter and optimizers will be installed and for opening
the Connection Unit drill guides. Use of an impact driver is
not
allowed.
Appropriate mounting hardware (for example: stainless bolts, nuts, and
washers) for attaching:
the inverter mounting bracket to the mounting surface
the power optimizer to the racking (not required for smart modules)
Wire cutters
EV Charging Single Phase Inverter Guide MAN-01-00404-1.2
16 Installation Procedure