Installation Guide
Table Of Contents
- Disclaimers
- Support and Contact Information
- Revision History
- Contents
- HANDLING AND SAFETY INSTRUCTIONS
- IMPORTANT SAFETY INSTRUCTIONS
- Chapter 1: Introducing the SolarEdge Power Harvesting System
- Chapter 2: Installing the Power Optimizers
- Chapter 3: Installing the Inverter
- Chapter 4: Connecting the AC and the Strings to the Safety Switch
- Chapter 5: Commissioning the Installation
- Chapter 6: User Interface
- Chapter 7: Setting Up Communication
- Appendix A: Errors and Troubleshooting
- Appendix B: Mechanical Specifications
- Appendix C: External Fan Maintenance and Replacement
- Appendix D: Replacing and Adding System Components
- Appendix E: Determining the Circuit Breaker Size
- Technical Specifications - Single Phase Inverters (North America)
- Technical Specifications - Three Phase Inverters (North America)

5. Verify that the inverter is configured to the proper country: Press the LCD light
button until reaching the ID status screen:
I D : # # # # # # # # # #
D S P 1 / 2 : 1 . 0 2 1 0 / 1 . 0 0 3 4
C P U : 0 0 0 3 . 1 9 x x
C o u n t r y : U S A 1
6.
If required, perform the following additional steps before closing the inverter cover:
Country settings or inverter configuration using the internal LCD user
buttons – refer to
Country and Grid
on page 66.
Communication options connection – refer to
Setting Up
Communication
on page 83.
7.
Close the inverter cover by tightening the screws with a torque of 10.3 N*M/ 7.5
lb*ft. For proper sealing, first tighten the corner screws and then the two central
screws. The following figure illustrates recommended order:
Figure 26: Tightening order of the screws
8. Ensure proper conduit sealing; inspect the entire conduit run and use standard
conduit sealants to avoid water penetration.
9.
Turn ON the Safety Switch. If an additional external DC switch is installed between
the power optimizers and the inverter(s) then turn it ON.
A status screen similar to the following appears on the LCD panel:
V a c [ V ] V d c [ V ] P a c [ w ]
2 4 0 . 7 1 4 . 1 0 . 0
P _ O K : 0 0 0 / 0 0 0 < S _ O K >
- - - - - - - - - - - - - - - O F F
10. Verify that the following information appears on the LCD panel:
-Three Phase System Installation Guide MAN-01-00002-4.3
54 Step 1: Activating the System