Installation Manual
Table Of Contents
- Disclaimers
- Contents
- HANDLING AND SAFETY INSTRUCTIONS
- Chapter 1: Overview
- Chapter 2: Installing the Power Optimizers
- Chapter 3: Installing the Inverter
- Chapter 4: Auto-transformer and Backed-up Loads Panel Installation (for Backup Only)
- Chapter 5: Electricity Meter Installation
- Chapter 6: StorEdge Inverter Connections
- Chapter 7: User Interface
- Chapter 8: Commissioning the Installation
- Chapter 9: System Configuration
- Chapter 10: Setting Up Communication to the Monitoring Portal
- Appendix A: Troubleshooting
- Appendix B: Replacing and Adding System Components
9. UnscrewthetwoconduitnutssecuringtheStorEdgeConnectionUnittotheexternalconduits.
10. ReleasethebracketsecuringtheStorEdgeConnectionUnittothewall.
11. CarefullyremovetheStorEdgeConnectionUnitwithitsmountingbracketfromthewall.
Installing a New StorEdge Connection Unit
1. OpentheStorEdgeConnectionUnitcover.
2. PositionthenewStorEdgeConnectionUnitbelowtheinverterandfromtheinsideoftheinverter
grabtheACandDCwiresextendingfromtheunitconduits,asshownbelow:
Figure 43: Inserting the AC and DC conduits
3. AttachtheStorEdgeConnectionUnitwithitsbrackettothewallandslightlyclosethescrews.Donot
overtighten.
4. ForRGMinverters-InsertthemeterRS485cablethroughtheDCsideconduitoftheStorEdge
ConnectionUnitandconnecttotheinvertercommunicationboard.
5. ReconnectthecablefromtheinverterdigitalboardtotheStorEdgeConnectionUnit.
6. Reconnectalltheexternalwiresandferritebeads..
7. Securelyscrewthetwoconduitnutsontotheconduitendsintheinverter.Verifyproperconduit
sealing.
8. ClosetheStorEdgeConnectionUnitcover.Attachthecoverandsecureitbytighteningthesixscrews
withatorqueof1.2N*m/0.9ft.*lb.
Appendix B: Replacing and Adding System Components
SolarEdge-StorEdge Installation Guide MAN-01-00262-1.0
93