Installation Manual
Table Of Contents
- Disclaimers
- Contents
- HANDLING AND SAFETY INSTRUCTIONS
- Chapter 1: Overview
- Chapter 2: Installing the Power Optimizers
- Chapter 3: Installing the Inverter
- Chapter 4: Auto-transformer and Backed-up Loads Panel Installation (for Backup Only)
- Chapter 5: Electricity Meter Installation
- Chapter 6: StorEdge Inverter Connections
- Chapter 7: User Interface
- Chapter 8: Commissioning the Installation
- Chapter 9: System Configuration
- Chapter 10: Setting Up Communication to the Monitoring Portal
- Appendix A: Troubleshooting
- Appendix B: Replacing and Adding System Components
Verifying the Connection
Afterconnectingandconfiguringacommunicationoption,performthefollowingstepstocheckthat
theconnectiontothemonitoringserverhasbeensuccessfullyestablished.
1.
Closetheinvertercover:Attachtheinvertercoverandsecureitbytighteningthescrewswitha
torqueof9.0N*m/6.6lb.*ft.Forpropersealing,firsttightenthecornerscrewsandthenthetwo
centralscrews(seealsoFigure28).
2. TurnONtheACtotheinverterbyturningONthecircuitbreakeronthemaindistributionpaneland
turningontheSafetySwitch.
3. WaitfortheinvertertoconnecttotheSolarEdgemonitoringportal.Thismaytakeuptotwo
minutes.
AstatusscreensimilartothefollowingappearsontheLCDpanel:
V a c [ V ] V d c [ V ] P a c [ w ]
2 4 0 . 7 1 4 . 1 0 . 0
P _ O K : 0 0 0 / 0 0 0 < S _ O K >
- - - - - - - - - - - - - - - O F F
S_OK:IndicatesthattheconnectiontotheSolarEdgemonitoringportalissuccessful.IfS_OKisnot
displayed,referto"Troubleshooting"onthefacingpage.
SolarEdge-StorEdge Installation Guide MAN-01-00262-1.0
78
Verifying the Connection