Installation Manual
Table Of Contents
- Disclaimers
- Contents
- HANDLING AND SAFETY INSTRUCTIONS
- Chapter 1: Overview
- Chapter 2: Installing the Power Optimizers
- Chapter 3: Installing the Inverter
- Chapter 4: Auto-transformer and Backed-up Loads Panel Installation (for Backup Only)
- Chapter 5: Electricity Meter Installation
- Chapter 6: StorEdge Inverter Connections
- Chapter 7: User Interface
- Chapter 8: Commissioning the Installation
- Chapter 9: System Configuration
- Chapter 10: Setting Up Communication to the Monitoring Portal
- Appendix A: Troubleshooting
- Appendix B: Replacing and Adding System Components
Chapter 8: Commissioning the Installation
Thischapterdescribeshowtoactivatethesystem,pairthepoweroptimizerstotheinverterandverify
theproperfunctioningofthesystem.
Step 1: Activating the System
1. VerifythattheinverterON/OFFswitchisOFF.
2. MovetheStorEdgeConnectionUnitON/OFFswitchtotheONposition.
WARNING!
ELECTRICAL SHOCK HAZARD. Do not touch uninsulated wires when the inverter cover is
removed.
RISQUE D’ÉLECTROCUTION, ne touchez pas les fils non isolés lorsque le couvercle de
l'onduleur est retiré.
Chapter 8: Commissioning the Installation
SolarEdge-StorEdge Installation Guide MAN-01-00262-1.0
55