Installation Manual
Table Of Contents
- Disclaimers
- Contents
- HANDLING AND SAFETY INSTRUCTIONS
- Chapter 1: Overview
- Chapter 2: Installing the Power Optimizers
- Chapter 3: Installing the Inverter
- Chapter 4: Auto-transformer and Backed-up Loads Panel Installation (for Backup Only)
- Chapter 5: Electricity Meter Installation
- Chapter 6: StorEdge Inverter Connections
- Chapter 7: User Interface
- Chapter 8: Commissioning the Installation
- Chapter 9: System Configuration
- Chapter 10: Setting Up Communication to the Monitoring Portal
- Appendix A: Troubleshooting
- Appendix B: Replacing and Adding System Components
Connecting to DC
Connecting the PVStrings
Figure 18: PV connection
1. VerifythattheACcircuitbreakerisOFF.
2. Strip5⁄16''(8mm)oftheDCwireinsulation.
3. InserttheDCconduitintotheDC-sideopening.Makesuretheconduitisfirmlyattachedtothe
inverterenclosureandsealedproperly.
4.
ConnecttheDCwiresfromthePVinstallationtotheDC+andDC-terminalblocks,accordingtothe
labelsontheterminals:
a. Insertaflatbladescrewdriverintothesquareopeningatthetopoftheterminalblockandpress
toopenclampmechanism.
b.
Insertthewireintotheroundopeningandreleasethescrewdrivertospringbackandclampthe
wire.Checkthatthewireisfullyinsertedandcannotbepulledouteasily.
CAUTION!
Ensure that the Plus (+) wire is connected to the Plus (+) terminal and that the Minus (-) wire is
connected to the Minus (-) terminal connector.
Veillez à ce que le câble Plus (+) soit connecté au terminal (+) et que le câble Minus (-) soit
connecté au connecteur terminal (-).
NOTE
For systems with three PV strings or more, fuses may need to be installed in both the positive
and negative conductors as required by Article 690.35(B). For more information, refer to the
Technical Note “String Fusing Requirements in SolarEdge Systems” at
http://www.solaredge.com/files/pdfs/string_fusing_requirements.pdf.