Power Control
The Grid Control option may be disabled. Enabling it opens additional options in the
menu.
The Energy Manager option is used for setting power export limitation,
as described in the
Export Limitation Application Note
, available on the
SolarEdge website at
https://www.solaredge.com/sites/default/files/export_limitation_
application_note_NA.pdf.
For P(Q) diagram refer to
https://www.solaredge.com/sites/default/files/application_note_p_q_
diagram_of_se_inverters_en_and_na.pdf.
NOTE
SolarEdge inverters with “Grid Support” functionality (as marked on the
inverter certification label), are compliant with UL1741 Supplement A. The
functionality is built into the inverter and no additional external device is
required.
Step 3: Verifying Proper Activation and
Commissioning
1. Select Information and verify that the correct firmware versions are installed on each
inverter.
2. Select Status and verify that inverter is operating and producing power.
3. Verify that additional configurations were properly set by viewing the relevant
Status screens.
4. Verify that the green inverter LEDis steadily lit.
Your SolarEdge power harvesting system is now operational.
Configuring Communication with Other Devices
If the above devices have not been auto-detected during system activation, configure
them as explained below.
To set up communication with the battery:
1.
Access SetApp and select Commissioning > Site Communication.
2.
From the Site Communication screen, select RS485-1 > Protocol > Modbus (Multi-
Single Phase Energy Hub Inverter with Prism Technology MAN-01-00671-1.3