Energy Hub with Prism Technology Installation Guide
Table Of Contents
- Disclaimers
- Revision History
- HANDLING AND SAFETY INSTRUCTIONS
- IMPORTANT SAFETY INSTRUCTIONS
- Chapter 1: Overview
- Chapter 2: Installing the Power Optimizer
- Chapter 3: Installing the Inverter
- Chapter 4: Installing the Battery
- Chapter 5: Connecting the Inverter
- Chapter 6: Activating, Commissioning and Configuring the System
- Chapter 7: Setting Up Communication to the Monitoring Platform
- Appendix A: Errors and Troubleshooting
- Appendix B: Mechanical Specifications
- Appendix C: Replacing and Adding System Components
- Appendix D: Powering the LG Chem Battery Off and On
- Single Phase Energy Hub Inverter with Prism Technology - Technical Specificat...
- Support Contact Information
Chapter 6: Activating, Commissioning and
Configuring the System
You can connect communication options at this stage, as described in
Setting Up
Communication to the Monitoring Platform
on page 54.
After completing all connections, activate and commission the system using the
inverter SetApp mobile application. You can download the SetApp from the Apple App
Store and Google Play before arriving at the site.
Internet connection is required for the download, one-time registration, and logging in,
but not required for using the SetApp.
Step 1: Activating the Installation
During system activation, a Wi-Fi connection is created between the mobile device and
the inverter and the system firmware is upgraded.
Before activation
Download, register (first time only)and log-in to SetApp on your mobile device.
Verify that the application is updated with the latest version.
If applicable, turn on all devices (battery, Energy Meter, Backup Interface)
connected to the inverter, so that the devices may be auto-detected.
To activate the inverter:
1. Turn ONthe ACcircuit breaker on the main distribution panel.
2.
Open SetApp and follow the on-screen instructions (scan the inverter bar-code;
move the ON/OFF/P switch to P position for 2 seconds and release).
SetApp creates a Wi-Fi connection, upgrades the inverter firmware and activates the
inverter.
Chapter 6: Activating, Commissioning and Configuring the System 45
Single Phase Energy Hub Inverter with Prism Technology MAN-01-00671-1.3