Energy Hub with Prism Technology Installation Guide
Table Of Contents
- Disclaimers
- Revision History
- HANDLING AND SAFETY INSTRUCTIONS
- IMPORTANT SAFETY INSTRUCTIONS
- Chapter 1: Overview
- Chapter 2: Installing the Power Optimizer
- Chapter 3: Installing the Inverter
- Chapter 4: Installing the Battery
- Chapter 5: Connecting the Inverter
- Chapter 6: Activating, Commissioning and Configuring the System
- Chapter 7: Setting Up Communication to the Monitoring Platform
- Appendix A: Errors and Troubleshooting
- Appendix B: Mechanical Specifications
- Appendix C: Replacing and Adding System Components
- Appendix D: Powering the LG Chem Battery Off and On
- Single Phase Energy Hub Inverter with Prism Technology - Technical Specificat...
- Support Contact Information
Figure 10: LEDs
The following table describes system performance information by LED color and
ON/OFF/P switch position.
Indication
ON/ OFF/
P
Switch
Position
LEDColor
Comment
Red Green Blue
Power
optimizers not
paired
ON (1)
OFF Blinking
S_OK: ON
No S_OK: OFF
S_OK: ON
communication
with the
monitoring
platform is
established.
Pairing Blinking Blinking Blinking
Wake-up/ Grid
Monitoring
OFF Blinking Blinking
System
Producing
OFF ON
S_OK: ON
No S_OK: OFF
Night mode
(no production)
OFF Flickering
S_OK: ON
No S_OK: OFF
Inverter is OFF
(Safe DC)
OFF (0)
OFF Blinking
S_OK: ON
No S_OK: OFF
Inverter is OFF
(DC not safe)
Blinking Blinking
S_OK: ON
No S_OK: OFF
Inverter
configuration
or reboot
ON / P ON ON ON
Chapter 3: Installing the Inverter 29
Single Phase Energy Hub Inverter with Prism Technology MAN-01-00671-1.3