Energy Hub with Prism Technology Installation Guide

Table Of Contents
AC conduit entry - For AC connection to the grid or Backup Interface
PVconduit entry - For DCconnection to SolarEdge Power Optimizers
EVconduit entry - For ACconnection to the Standalone EVCharger
Battery conduit entry - For DCconnection to the battery
DCSafety switch - connects and disconnects the DC power to the system
Two communication glands: for connection of inverter communication options.
Each gland has three openings.
ON/OFF/P switch:
Figure 9: ON/OFF/P switch
ON (1) - Turning this switch ON (after power optimizer pairing) starts the
operation of the power optimizers, enables power production and allows the
inverter to begin exporting power to the utility grid.
OFF (0) - Turning this switch OFF reduces the power optimizer voltage to a low
safety voltage and inhibits exportation of power. When this switch is OFF, the
control circuitry remains powered up.
Chapter 3: Installing the Inverter 27
Single Phase Energy Hub Inverter with Prism Technology MAN-01-00671-1.3