SE6000HD-US Installation Manual
Table Of Contents
- Disclaimers
- Revision History
- HANDLING AND SAFETY INSTRUCTIONS
- IMPORTANT SAFETY INSTRUCTIONS
- Chapter 1: Introducing the SolarEdge Power Harvesting System
- Chapter 2: Installing the Power Optimizers
- Chapter 3: Installing the Inverter
- Chapter 4: Connecting the AC and the Strings to the Safety Switch
- Chapter 5: Activating, Commissioning and Configuring the System
- Chapter 6: Setting Up Communication to the Monitoring Platform
- Appendix A: Errors and Troubleshooting
- Appendix B: Mechanical Specifications
- Appendix C: Replacing and Adding System Components
- Technical Specifications - Single Phase Inverters with HD-Wave Technology (No...
- Support Contact Information
Chapter 4: Connecting the AC and the Strings
to the Safety Switch
The Safety Switch disconnects all ungrounded DC conductors of the circuit to which it
is connected in compliance with the National Electric Code, and specifically NEC690.35,
which addresses ungrounded PV arrays. The Safety Switch is rated to the maximum
operating conditions of the inverter.
NOTE
For systems with an integrated production and export/import
meter:
To install and activate the export/import metering function,
refer to the document:
https://www.solaredge.com/sites/default/files/se-inverters-with-rgm-
and-export-import-meter-na.pdf
The following figure illustrates the Safety Switch
Figure 19: Inside the Safety Switch
Single Phase Inverter with HD-Wave Technology Installation MAN-01-00541-1.4
36 Chapter 4: Connecting the AC and the Strings to the Safety Switch