SE6000HD-US Installation Manual
Table Of Contents
- Disclaimers
- Revision History
- HANDLING AND SAFETY INSTRUCTIONS
- IMPORTANT SAFETY INSTRUCTIONS
- Chapter 1: Introducing the SolarEdge Power Harvesting System
- Chapter 2: Installing the Power Optimizers
- Chapter 3: Installing the Inverter
- Chapter 4: Connecting the AC and the Strings to the Safety Switch
- Chapter 5: Activating, Commissioning and Configuring the System
- Chapter 6: Setting Up Communication to the Monitoring Platform
- Appendix A: Errors and Troubleshooting
- Appendix B: Mechanical Specifications
- Appendix C: Replacing and Adding System Components
- Technical Specifications - Single Phase Inverters with HD-Wave Technology (No...
- Support Contact Information
The main LED indications are:
Blue ON - the inverter is communicating with the monitoring platform
Green ON- the system is producing
Green blinking - AC is connected but the system is not producing
Red ON - system error
Figure 12: LEDs
The following table describes system performance information by LED color and
ON/OFF/P switch position.
Indication
ON/ OFF/
P
Switch
Position
LEDColor
Comment
Red Green Blue
Power
optimizers not
paired
ON (1)
OFF Blinking
S_OK: ON
No S_OK: OFF
S_OK: ON
communication
with the
monitoring
platform is
established.
Pairing Blinking Blinking Blinking
Wake-up/ Grid
Monitoring
OFF Blinking Blinking
System
Producing
OFF ON
S_OK: ON
No S_OK: OFF
Night mode
(no production)
OFF Flickering
S_OK: ON
No S_OK: OFF
Inverter is OFF
(Safe DC)
OFF (0)
OFF Blinking
S_OK: ON
No S_OK: OFF
Inverter is OFF
(DC not safe)
Blinking Blinking
S_OK: ON
No S_OK: OFF
Chapter 3: Installing the Inverter 29
Single Phase Inverter with HD-Wave Technology Installation MAN-01-00541-1.4