Installation Guide

7. Perform pairing as described in
Activating, Commissioning and Configuring the
System Using the Inverter SetApp
on page 51.
Replacing the Connection Unit
Removing the Connection Unit
1. Turn OFF the Inverter ON/OFF switch, and wait until the green LED is blinking
,indicating that the DC voltage is safe (<50V), or wait five minutes before continuing
to the next step.
WARNING!
If you cannot see Primary Unit LEDs or you cannot connect to the Primary
Unit, or if the red LED light is on indicating a malfunction, wait five minutes
for the input capacitors of the inverter to discharge.
AVERTISSEMENT!
Si vous ne pouvez pas voir les LED de l'unité principale ou si vous ne pouvez
pas vous connecter à l'unité principale, ou si le voyant LED rouge s'allume,
attendez cinq minutes que les condensateurs d'entrée de l'onduleur se
déchargent.
2. Disconnect the AC to the inverter by turning OFF the circuit breakers on the
distribution panel.
3.
Open the Connection Unit cover:
Release the six Allen screws of the cover.
Tilt the top of the cover towards you.
Slide the cover down and remove it.
CAUTION!
When removing the cover, make sure not to damage internal components.
SolarEdge will not be held responsible for any components damaged as a result
of incautious cover removal.
ATTENTION!
Lors du retrait du couvercle, assurez-vous de ne pas endommager les
composants internes. SolarEdge ne peut être tenue pour responsable des
composants endommagés à la suite d'une imprudence dans le retrait du
couvercle.
4. Disconnect the Secondary Unit(s) from the Connection Unit .
Three Phase Inverter with Synergy Technology Installation MAN-01-00401-1.5
96 Replacing the Connection Unit