Installation Guide

Verifying the Connection
After connecting and configuring a communication option, perform the following
steps to check that the connection to the monitoring server has been successfully
established.
1. If the Connection Unit cover is not closed, close it: Attach the Connection Unit cover
and secure it by tightening the screws with a torque of 10.3 N*m/ 7.5 lb.*ft.For
proper sealing, first tighten the corner screws and then the two central screws.
2.
Access the Status screen:
a. If not already ON - turn ON AC to the inverter by turning ON the circuit breaker
on the main distribution panel.
b. If not already ON - move the Connection Unit switch to the ON position.
c.
Open SetApp and follow the instructions on the screen (scan the inverter bar-
code; move the ON/OFF/P switch to P position (for less than 5 sec) and release).
The mobile device creates a Wi-Fi connection with the inverter and displays the
main Commissioning screen.
Status
Inverter
SN 07318000C
Power
100 kW
Voltage
277 Vac
Frequency
60.9 Hz
P_OK: 138 of 141
Optimizers
Connected
S_OK
Server Connected
Status
Production
Switch
ON
CosPhi
1.00
Limit
No Limit
Country
USA2
Voltage
850 Vdc
Temp
156 F
Fan
OK
Commissioning
3.
Check that S_OK- Server Connected status appears in the main inverter section.
Chapter 6: Setting Up Communication 81
Three Phase Inverter with Synergy Technology Installation MAN-01-00401-1.5