Installation Guide

Temporarily displayed (with a clock sign):
Initializing communication
Connecting to a network
Connecting to SolarEdge servers
Error message (with the sign). Refer to
Troubleshooting Communication
on
page 87.
Inverter Energy Status
Displays the total energy produced during the last day, month, year and since inverter
installation.
Inverter Energy
Today
45 kWh
This Month
1.14 MWh
This Year
13.68 MWh
Total: 41.03 MWh
Today: since midnight
This Month: since 1st of the current month
This Year: since January 1st
Total (Wh): The inverter total energy. If an external meter is installed, the value
displayed in this line depends on the meter type connected to the inverter and
its location:
If a bidirectional meter is connected at the consumption point, this
value is the consumed energy.
If the meter is installed at the production point, this value is the energy
produced by the site.
If the meter is installed at the grid connection point, this value is the
energy exported to the grid.
Chapter 5: Activating, Commissioning and Configuring the System Using the
Inverter SetApp 63
Three Phase Inverter with Synergy Technology Installation MAN-01-00401-1.5