Installation Guide
CPU Version: The communication board firmware version
DSP 1/2 Version: The digital board firmware version
NOTE
Please have these numbers ready when you contact SolarEdge Support.
Serial Number - The inverter serial number as appears on the enclosure sticker
Hardware IDs: Displays the following HW serial numbers (if exist, and
connected to the inverter):
This inverter: the inverter's ID
Meter # : Energy meter ID (up to 3 meters can be connected)
ZB: ZigBee Plug-in MAC address
Cell: MEID (CDMA) or IMEI (GSM)
Error Log: Displays the last five errors, and enables resetting (clearing) the log.
Warning Log: Displays the last five warnings, and enables resetting (clearing)
the log.
Step 3: Verifying Proper Activation and
Commissioning
1. Select Information and verify that the correct firmware versions are installed on each
inverter.
2. Select Status and verify that inverter is operating and producing power (see also
Viewing System Status
on page 58).
3. Verify that the number of paired optimizers is the same as the number of physically
installed power optimizers.
4. Verify that additional configurations were properly set by viewing the relevant
Status screens.
5. Verify that the green inverter LEDis steadily lit.
Your SolarEdge power harvesting system is now operational.
Chapter 5: Activating, Commissioning and Configuring the System Using the
Inverter SetApp 57
Three Phase Inverter with Synergy Technology Installation MAN-01-00401-1.5