Installation Guide

If the inverter has already been activated and commissioned:
If not already ON - turn ON AC to the inverter by turning ON the circuit
breaker on the main distribution panel.
If not already ON - move the Connection Unit switch to the ON position.
Open SetApp and follow the instructions on the screen (scan the inverter
bar-code; move the ON/OFF/P switch to P position (for less than 5 sec) and
release).
The mobile device creates a Wi-Fi connection with the inverter and displays
the main Commissioning screen.
In the main menus, tap the menu red arrows ()to perform the system commissioning
or configuration task. Tap the Back arrow () to return to the previous menu.
The next sections provide more information about configuration options (in addition to
Country and Language and Pairing, described in
Step 2: Commissioning and
Configuring the Installation
on page 52).
Setting Country and Language
1.
From the Commissioning screen select Country and Language .
2.
From the Country drop-down list, select the required country setting.
WARNING!
The inverter must be configured to the proper setting in order to ensure that
it complies with the country grid code and functions properly with the
country grids.
AVERTISSEMENT!
L'onduleur doit être configuré pour le pays approprié afin d'assurer un
fonctionnement convenable avec le seau de ce pays.
3. From the Language drop-down list, select the language.
4. Tap Set Language.
Pairing
Once all connections are made, all the power optimizers must be logically paired to
their inverter. The poweroptimizers do not start producing power until they are paired.
This step describes how to assign each inverter to the poweroptimizers from which it
will produce power.
Chapter 5: Activating, Commissioning and Configuring the System Using the
Inverter SetApp 53
Three Phase Inverter with Synergy Technology Installation MAN-01-00401-1.5