Installation Guide

Open the DC entry cover. If needed, knockout the DCdrill guide.
NOTE
The Connection Unit is provided with one open DC conduit
opening and with one closed drill guide. If you require an
additional conduit entry, open the drill guide.
Open the AC conduit entry.
If using one Secondary Unit, open the drill guide according to the smaller
size marking. If using two Secondary Units you can open it to a larger
diameter according to the cable size.
NOTE
Unused conduit openings and glands should be sealed with appropriate seals.
Mounting and Connecting the Primary and Secondary
Unit(s)
The inverter is typically mounted vertically, and the instructions in this
section are applicable for vertical installation. Some SolarEdge inverters
model can be installed horizontally (above 10° tilt) as well as vertically.
For information and instructions for horizontal mounting refer to
http://www.solaredge.com/sites/default/files/application_note_horizontal_
mounting_of_three_phase_inverters.pdf
First mount the Primary Unit then the Secondary Unit(s).
Figure 17: Mounting bracket
NOTE
Make sure the mounting surface or structure can support the weight of the
inverter and brackets, and make sure that it spans the width of the mounting
brackets.
Three Phase Inverter with Synergy Technology Installation MAN-01-00401-1.5
36 Mounting and Connecting the Primary and Secondary Unit(s)