Installation Guide
The Rapid Shutdown (PVRSS)is initiated by one of the following methods:
Inverter AC breaker is turned OFF, or AC to the inverter is disconnected
by another method (intentionally or as result of a fault)
Inverter ON/OFF switch is turned OFF
The Connection Unit is turned OFF
Each power optimizer also transmits module performance data over the DC power line
to the inverter.
Two types of power optimizers are available:
Module Add-on power optimizer – connected to one or more modules
Smart modules - the power optimizer is embedded into a module
Three Phase Inverter with Synergy Technology
The Three Phase Inverter with synergy technology inverter (referred to as 'inverter' in
this manual ) efficiently converts DC power from the modules into AC power that can
be fed into the main ACservice of the site and from there to the grid. The inverter also
receives the monitoring data from each power optimizer and transmits it to the
SolarEdge monitoring platform (requires Internet or Cellular connection).
The inverter is comprised of one Primary Unit with an integrated Connection Unit with a
DC Safety Switch (referred to as 'Connection Unit ' in this manual) for disconnecting the
DCpower of a SolarEdge system, and of one or two Secondary Units, depending on the
inverter's capacity. The Secondary Unit(s) are connected to the primary unit with AC, DC
and communication cables.
Each unit operates independently and continues to work in case the others are not
operating.
You can set up a master- slave configuration, connecting up to 31 additional inverters
to one master inverter.
Three Phase Inverter with Synergy Technology Installation MAN-01-00401-1.5