Install Manual
Table Of Contents
- Disclaimers
- Revision History
- HANDLING AND SAFETY INSTRUCTIONS
- IMPORTANT SAFETY INSTRUCTIONS
- Chapter 1: Overview
- Chapter 2: Installing the Power Optimizer
- Chapter 3: Installing the Inverter
- Chapter 4: Installing the Battery
- Chapter 5: Connecting the Inverter
- Chapter 6: Activating, Commissioning and Configuring the System
- Chapter 7: Setting Up Communication to the Monitoring Platform
- Appendix A: Errors and Troubleshooting
- Appendix B: Mechanical Specifications
- Appendix C: Replacing and Adding System Components
- Appendix D: Powering the LG Chem Battery Off and On
- Single Phase Energy Hub Inverter with Prism Technology - Technical Specificat...
- Support Contact Information
4.
Connect the communication cable wires to the 8-pin connector, as shown below.
Figure 19: Communication cable connection - LGChem battery to the inverter
5. Make sure the three DIP switches above the connector are in the down position
(down - for RS485-2 the SolarEdge protocol; up - for RS485-1 the Modbus protocol).
6. Pass the other end of the DCcable through the Battery conduit.
7.
Connect the wires to the DCterminals, as shown below.
WARNING!
Make sure to connect the power cables at correct polarity. Connecting the
power cables at reverse polarity may result in damage to the inverter or
battery.
Figure 20: DC cable connection - LGChem battery to the inverter
Connecting the Backup Interface
The Backup Interface must be installed to allow the operation of batteries.
When connecting the Backup Interface to the inverter, use the following cable types:
AC- 14-6 AWG cable
Communication - 5-wire shielded twisted pair cable, 24 AWG (16-24 AWG), 600V