Install Manual
Table Of Contents
- Disclaimers
- Revision History
- HANDLING AND SAFETY INSTRUCTIONS
- IMPORTANT SAFETY INSTRUCTIONS
- Chapter 1: Overview
- Chapter 2: Installing the Power Optimizer
- Chapter 3: Installing the Inverter
- Chapter 4: Installing the Battery
- Chapter 5: Connecting the Inverter
- Chapter 6: Activating, Commissioning and Configuring the System
- Chapter 7: Setting Up Communication to the Monitoring Platform
- Appendix A: Errors and Troubleshooting
- Appendix B: Mechanical Specifications
- Appendix C: Replacing and Adding System Components
- Appendix D: Powering the LG Chem Battery Off and On
- Single Phase Energy Hub Inverter with Prism Technology - Technical Specificat...
- Support Contact Information
Connecting the Inverter to ACGrid
For connecting the inverter to ACgrid, use a 14-4 AWG cable.
For more wiring information refer to the
SolarEdge Recommended AC
Wiring Application Note
, available on the SolarEdge website at
http://www.solaredge.com/files/pdfs/application-note-recommended-
wiring.pdf.
To connect to ACgrid:
1. Turn off the AC circuit breaker on the distribution panel.
2.
Strip 2.8'' / 70 mm of the external cable insulation and strip 0.32'' / 8 mm of the
internal wire insulation.
Figure 16: Insulation Stripping – AC Cable
3. Pass the ACcable through the conduit.
4.
Connect the wires to the ACterminals as shown below.
Figure 17: AC connection
Connecting the DC Strings to the Inverter
Connect the string to the DC input pairs. If required, connect additional strings in
parallel using an external combiner box/branch cables before connecting to the
inverter.
Chapter 5: Connecting the Inverter 37
Single Phase Energy Hub Inverter with Prism Technology MAN-01-00671-1.2