Install Manual
Table Of Contents
- Disclaimers
- Revision History
- HANDLING AND SAFETY INSTRUCTIONS
- IMPORTANT SAFETY INSTRUCTIONS
- Chapter 1: Overview
- Chapter 2: Installing the Power Optimizer
- Chapter 3: Installing the Inverter
- Chapter 4: Installing the Battery
- Chapter 5: Connecting the Inverter
- Chapter 6: Activating, Commissioning and Configuring the System
- Chapter 7: Setting Up Communication to the Monitoring Platform
- Appendix A: Errors and Troubleshooting
- Appendix B: Mechanical Specifications
- Appendix C: Replacing and Adding System Components
- Appendix D: Powering the LG Chem Battery Off and On
- Single Phase Energy Hub Inverter with Prism Technology - Technical Specificat...
- Support Contact Information
Make sure to use power optimizers that have the required output conductor length.
Completely shaded panels may cause their power optimizers to temporarily shut
down. This will not affect the performance of the other power optimizers in the
string, as long as the minimum number of unshaded power optimizers connected in
a string of modules is met. If under typical conditions fewer than the minimum
power optimizers are connected to unshaded panels, add more power optimizers to
the string.
Equipment grounding tightening torques: 4-6 AWG: 45 lb-in, 8 AWG: 40 lb-in, 10-14
AWG: 35 lb-in.
To allow for heat dissipation, maintain clearance as specified below.
Figure 2: Power optimizer clearance
When installing panels in a confined space, for example, if installing Building-
integrated photovoltaic (BIPV) panels, ventilation measures may be needed to
ensure the power optimizers are not be exposed to temperatures outside their
specifications.
Chapter 2: Installing the Power Optimizer 19
Single Phase Energy Hub Inverter with Prism Technology MAN-01-00671-1.2