Energy Hub with Prism Technology Installation Guide

Table Of Contents
Test Results Solution
Charge failed
Check that the power and communication cables
between the battery and inverter are properly
connected.
Discharge failed
Check that the power and communication cables
between the battery and inverter are properly
connected.
Communication
Check that the communication cables between the
battery and inverter are properly connected.
Inverter switch is off Switch the inverter ON/OFF/P switch to ON.
To show the last test results:
Select Commissioning è Maintenance è Diagnostics è Self-Test è Battery Self-
Test è Show Last Results.
Enabling StorEdge Applications
This section describes how to configure your system to use StorEdge applications.
Before enabling StorEdge applications, run a battery self-test, as described above.
Backup Power Applications
The produced power is stored in the battery to be used during power outages. When
the grid voltage is down, the Backup Interface automatically switches to the Backup
mode, disconnecting from the grid, while the Energy Hub inverter supplies power to
the backed-up loads. This application requires connection to the Backup Interface and
backed-up loads (pre-selected or the entire home).
The application can be used in one of two ways:
Backup-onlyenergy stored in the battery is discharged for backup power only,
that is, when there is no power from the grid
Backup with Smart Energy Managementuse some of the battery energy for
backup power, and the rest for maximize self-consumption(MSC) or charge/
discharge profile programming (for time of use arbitrage) applications.
The Backup application can be used whether or not PV modules are installed at the site.
The backup function is disabled by default and can be enabled for on- grid only
application, if backup is not needed.
Single Phase Energy Hub Inverter with Prism Technology MAN-01-00671-1.3
50 Enabling StorEdge Applications