Energy Hub with Prism Technology Installation Guide
Table Of Contents
- Disclaimers
- Revision History
- HANDLING AND SAFETY INSTRUCTIONS
- IMPORTANT SAFETY INSTRUCTIONS
- Chapter 1: Overview
- Chapter 2: Installing the Power Optimizer
- Chapter 3: Installing the Inverter
- Chapter 4: Installing the Battery
- Chapter 5: Connecting the Inverter
- Chapter 6: Activating, Commissioning and Configuring the System
- Chapter 7: Setting Up Communication to the Monitoring Platform
- Appendix A: Errors and Troubleshooting
- Appendix B: Mechanical Specifications
- Appendix C: Replacing and Adding System Components
- Appendix D: Powering the LG Chem Battery Off and On
- Single Phase Energy Hub Inverter with Prism Technology - Technical Specificat...
- Support Contact Information
AC conduit entry - For AC connection to the grid or Backup Interface
PVconduit entry - For DCconnection to SolarEdge Power Optimizers
EVconduit entry - For ACconnection to the Standalone EVCharger
Battery conduit entry - For DCconnection to the battery
DCSafety switch - connects and disconnects the DC power to the system
Two communication glands: for connection of inverter communication options.
Each gland has three openings.
ON/OFF/P switch:
Figure 9: ON/OFF/P switch
ON (1) - Turning this switch ON (after power optimizer pairing) starts the
operation of the power optimizers, enables power production and allows the
inverter to begin exporting power to the utility grid.
OFF (0) - Turning this switch OFF reduces the power optimizer voltage to a low
safety voltage and inhibits exportation of power. When this switch is OFF, the
control circuitry remains powered up.
Chapter 3: Installing the Inverter 27
Single Phase Energy Hub Inverter with Prism Technology MAN-01-00671-1.3