Energy Hub with Prism Technology Installation Guide
Table Of Contents
- Disclaimers
- Revision History
- HANDLING AND SAFETY INSTRUCTIONS
- IMPORTANT SAFETY INSTRUCTIONS
- Chapter 1: Overview
- Chapter 2: Installing the Power Optimizer
- Chapter 3: Installing the Inverter
- Chapter 4: Installing the Battery
- Chapter 5: Connecting the Inverter
- Chapter 6: Activating, Commissioning and Configuring the System
- Chapter 7: Setting Up Communication to the Monitoring Platform
- Appendix A: Errors and Troubleshooting
- Appendix B: Mechanical Specifications
- Appendix C: Replacing and Adding System Components
- Appendix D: Powering the LG Chem Battery Off and On
- Single Phase Energy Hub Inverter with Prism Technology - Technical Specificat...
- Support Contact Information
CAUTION!
All PV panels must be connected to a power optimizer.
ATTENTION!
Tous les modules doivent être connectés à un optimiseur de puissance.
CAUTION!
If you intend to mount the optimizers directly to the panel or panel frame, first
consult the panel manufacturer for guidance regarding the mounting location
and the impact, if any, on panel warranty. Drilling holes in the panel frame
should be done according to the panel manufacturer instructions.
ATTENTION!
Pour installation à même le module ou la monture du module, consultez
d'abord le fabricant du module sur la position et son impact sur la garantie du
module. Le perçage de trous dans le cadre du module devra se faire suivant les
instructions du fabricant.
CAUTION!
Installing a SolarEdge system without ensuring compatibility of the panel
connectors with the optimizer connectors may be unsafe and could cause
functionality problems such as ground faults, resulting in inverter shut down. To
ensure mechanical compatibility of the power optimizers’ connectors with the PV
panel’ connectors to which they are connected:
Use identical connectors from the same manufacturer and of the same type
on both the power optimizers and on the panels; or
Verify that the connectors are compatible in the following way:
The panel connector manufacturer should explicitly verify compatibility
with the SolarEdge optimizer connector; and
A third-party test report by one of the listed external labs (TUV, VDE,
Bureau Veritas UL, CSA, InterTek) should be obtained, verifying the
compatibility of the connectors.
For more information, refer to
https://www.solaredge.com/sites/default/files/optimizer-input-
connector-compatibility.pdf
Single Phase Energy Hub Inverter with Prism Technology MAN-01-00671-1.3
16 Safety