Fault current contribution:
Inverter
Inom [A]
Peak
[A]
1 cycle
RMS[A]
3 cycle
RMS[A]
Duration
(ms)
SE66.6K-US 50 118 40 24 30
SE100K-US 120 210 75 49.5 54
Duration - time by which fault current reaches 0
1 cycle RMS - the integral on one cycle (60Hz) duration
3 cycle RMS - the integral on 3-cycle duration
Default Trip Limits and Times According to IEEE1547
NOTE
The inverters are equipped with adjustable utility protective function set-points, and can be aggregated above 30kW on a single Point of Common Connection.
The default settings are in compliance with IEEE1547. Utility authorization is required to change these set-points.
Voltage Range (% of Base Voltage) Max. Clearing Time (Sec)
V < 50% 0.16
50 % < V < 88% 2.00
110% < V < 120 1.00
V > 120 % 0.16
Frequency Range (Hz) Max. Clearing Time (Sec)
> 60.5 0.16
< 59.3 (Hawaii 57) 0.16
5
Default Trip Limits and Times According to IEEE1547