Installation Manual

Inverter Energy Status
Displaysthetotalenergyproducedduringthelastday,month,yearandsinceinverterinstallation.
InverterEnergy
Today
45 kWh
This Month
1.14 MWh
This Year
13.68 MWh
Total: 41.03 MWh
l Today:sincemidnight
l This Month:since1stofthecurrentmonth
l This Year:sinceJanuary1st
l Total (Wh):Theinvertertotalenergy.Ifanexternalmeterisinstalled,thevaluedisplayedinthisline
dependsonthemetertypeconnectedtotheinverteranditslocation:
o
Ifabidirectionalmeterisconnectedattheconsumptionpoint,thisvalueistheconsumedenergy.
o
Ifthemeterisinstalledattheproductionpoint,thisvalueistheenergyproducedbythesite.
o
Ifthemeterisinstalledatthegridconnectionpoint,thisvalueistheenergyexportedtothegrid.
Meter Status
Meters
Production RS485-2 Modbus ID #2
Status: OK
Power: 7.60kW, Energy: 13.68MWh
Export GPIO S0 meter
1000 pulses per kWh
Power: 7.60kW, Energy: 13.68MWh
l Type and function:Displaysthemeterfunctionality(Production,Export,Import,Export+Import)
l Status:DisplaysOKifthemeteriscommunicatingwiththeinverter
l <Error message>:Ifthereisametererror,itisdisplayedinthisline.
l Power:Dependingonthemetertypeconnectedtotheinverter,thislinedisplaystheexportedor
importedpower
Chapter 5: Activating, Commissioning and Configuring the System Using SolarEdge
Three Phase Inverter with synergy technology Guide MAN-01-00401-1.1
54