Installation Manual

Step 3: Verifying Proper Activation and
Commissioning
1. SelectInformationandverifythatthecorrectfirmwareversionsareinstalledoneachinverter.
2. SelectStatusandverifythatinverterisoperatingandproducingpower(seealsoViewingSystem
Statusonpage50).
3. Verifythatthenumberofpairedoptimizersisthesameasthenumberofphysicallyinstalledpower
optimizers.
4. VerifythatadditionalconfigurationswereproperlysetbyviewingtherelevantStatusscreens.
5. VerifythatthegreeninverterLEDissteadilylit.
YourSolarEdgepowerharvestingsystemisnowoperational.
Reporting and Monitoring Installation Data
NOTE
This step requires connecting one of the communication options. Refer to Setting Up
Communication on page 56.
The SolarEdge Monitoring System
TheSolarEdgecloud-basedmonitoringplatformenablesaccessingSolarEdgesite
information,includingup-to-dateinformationviewedinaphysicalorlogicalview.The
monitoringplatformisdescribedindetailintheSolarEdgeMonitoringPlatformUser
Guide,availableontheSolarEdgewebsiteat
http://www.solaredge.us/files/pdfs/solaredge-monitoring-platform-user-guide.pdf.
TheSolarEdgemonitoringplatformcandisplaylogicalandphysicallayoutsofthe
installedsystem,asfollows:
l Logical Layout:Showsaschematiclogicallayoutofthecomponentsinthesystem,suchas:inverters,
stringsandmodules,aswellastheirelectricalconnectivity.Thisviewenablesyoutoseewhich
modulesareconnectedineachstring,whichstringsareconnectedtoeachinverter,andsoon.
l Physical Layout:Showsaschematicphysicallayoutofthecomponentsinthesystem,suchas:
inverters,stringsandmodules,aswellastheirelectricalconnectivity.Thisviewenablesabirdseye
viewoftheactuallocationofasystemcomponent.
Usingtheplatform,youcan:
l Viewthelatestperformanceofspecificcomponents.
l Findunder-performingcomponents,suchasmodules,bycomparingtheirperformancetothatof
othercomponentsofthesametype.
l Pinpointthelocationofalertedcomponentsusingthephysicallayout.
l Seehowcomponentsareconnectedtoeachother.
l Pairpoweroptimizersremotely.
Todisplayalogicallayout,inserttheinverterserialnumberinthenewsitecreatedintheapplication.
Whenthecommunicationbetweentheinverterandthemonitoringserverisestablished,thelogical
layoutisdisplayed.
Todisplayaphysicallayout,youneedtomapthelocationsoftheinstalledpoweroptimizers.Togenerate
aphysicalmapping,useeithertheSiteMapperapplicationorthephysicallayouteditorinthemonitoring
platform.
Chapter 5: Activating, Commissioning and Configuring the System Using SolarEdge
Three Phase Inverter with synergy technology Guide MAN-01-00401-1.1
48