Installation Manual

WARNING!
The metallic enclosure of the power optimizer must be grounded in accordance with the
requirements of the local and national codes.
L'enceinte métallique de l’optimiseur de puissance doit être mise à la terre en accord avec les
régulations locales et nationales.
l For mounting on a grounded metal rail:Usetheprovided5/16''stainlesssteelgroundingstar
washerbetweentherailingandtheflatsideofthemountingbracket.Thegroundingwasher
shouldbreakthroughtheanodizecoatingoftherailingtoensurelowresistiveconnection.Apply
torqueof9.5N*m/7lb*ft.SeeFigure5.
Figure 5: Power optimizer installation and grounding using a star washer
l For mounting on rails with sliding nut fasteners:Ifthestarwashercannotbeused,usethe
SolarEdgegroundingplate(purchasedseparately)betweentherailingandtheflatsideofthe
mountingbracket.Usemountingspecifichardwareasneeded.Applytorqueof9.5N*m/7lb*ft.
SeeFigure6
Figure 6: Power optimizer installation and grounding using a grounding plate
l For mounting on un-grounded structures(suchasawoodenstructure):Ifthestarwasheror
theplatecannotbeused,usetheSolarEdgegroundinglug(purchasedseparately)withan
equipment-groundingconductoraccordingtothesuppliedinstructions.Thegroundingterminal
acceptsawiresizeof6-14AWG,andmustbesizedforequipmentgroundingperNEC250.122
requirements.Tightenthescrewsconnectingthepoweroptimizertotheframeandthe
groundingterminalscrew.Applytorqueof9.5N*m/7lb*ft.SeeFigure7
Three Phase Inverter with synergy technology Guide MAN-01-00401-1.1
17
Step 1: Mounting and Grounding the Power Optimizers