Installation Guide
If the SolarEdge device is connected to the SolarEdge server this value will also be
displayed in the monitoring platform.
Troubleshooting the Dual-Meter Connection
To troubleshoot the Dual-Meter connection using SetApp,
Troubleshooting Dual-Meter
Connection Using SetApp
on page 39.
To troubleshoot the Dual-Meter connection using the device display,
Troubleshooting
Dual-meter Connection using the Device Display
on page 40.
Troubleshooting Dual-Meter Connection Using SetApp
For each of the meters installed, a dedicated Meters section should appear on the
Status Page, as shown below:
Meters
Inverter Production Meter
RS485-1
Modbus ID #1
Status
OK
Power
7.60 kW
Energy
13.68 MWh
Export Meter
RS485-1
Modbus ID #2
Status
OK
Power
7.60 kW
Energy
8.42 MWh
If one or more of the meters is missing from the Meters section shown above, check the
following:
The meters are configured as described in "Configuring the Dual-Meter
Connection" on page35
There are no loose connections at the inverter connectors and at the meters,
specifically the RS485 wiring.
Appendix B: Installing Two Meters 39
Energy Meter with Modbus Connection MAN-01-00270-1.3