Installation Guide

Site Production: The meter is installed at the inverter output and reads the
energy produced by inverters at the site.
Ext. Production: The meter is used for export limitation with 3rd party generators
and for AC coupling with non-SolarEdge inverters.
6. Select Meter Protocol, and select SolarEdge.
7. Select Device ID and enter the Modbus address corresponding to the ID DIP switch
settings on the meter.
8. Select CT Rating and enter the current transformer's rating in amperes.
9. Select Grid Topology and select Wye.
10. If relevant, select PT Scaling and set the potential transformer ratio. The default
value is 1.
To verify the meter connection using SetApp:
1. From the SetApp main menu, select Status.
2. On the Status page, scroll down to the Communication section and view the current
connection state.
Meters
Export Meter
RS485-2
Modbus ID #1
Status
OK
Power
7.60 kW
Energy
13.68 MWh
Device Configuration using the Device Display Menus
To operate the SolarEdge device menus:
Use the four user buttons to control the LCD panel menus:
Esc: Moves the cursor (>) to the beginning of the currently displayed parameter;
goes to the previous menu, and cancels a value change with a long press (until
Aborted is displayed).
Up (1) and Down (2): Moves the cursor from one menu option to another, moves
among the characters of a displayed parameter, and toggles between possible
characters when setting a value.
Energy Meter with Modbus Connection MAN-01-00270-1.3
22 Device Configuration