Installation Guide

Figure 13: Meter - rear view
6.
Mount the meter: Attach the meter enclosure's back brackets to the mounted
bracket using the four supplied screws. Tighten the screws with a torque of 9 N*m /
6.6 lb*ft.
To install the current transformers (CTs):
CAUTION!
NOTE
CTs are not supplied with the meter and must be purchased separately.
Rogowski coils are
not
suitable for use with the meter.
1. Turn off AC power before clamping on current transformers.
2. Install the CTs around the conductor to be measured. Split-core CTs can be opened
for installation around a conductor. A nylon cable tie may be secured around the CT
to prevent accidental opening.
3. Install the CTs with the arrows pointing to the grid for consumption or export
measurement.