P400 Installation
Table Of Contents
- SolarEdge Installation Guide - North America Version 4.0
- Disclaimers
- Support and Contact Information
- Contents
- HANDLING AND SAFETY INSTRUCTIONS
- IMPORTANT SAFETY INSTRUCTIONS
- Chapter 1: Introducing the SolarEdge Power Harvesting System
- Chapter 2: Installing the Power Optimizers
- Chapter 3: Installing the Inverter
- Chapter 4: Connecting the AC and the Strings to the Safety Switch
- Chapter 5: Commissioning the Installation
- Chapter 6: User Interface
- Chapter 7: Setting Up Communication
- Appendix A: Errors and Troubleshooting
- Appendix B: Technical Specifications
- Appendix C: Mechanical Specifications
- Appendix D: External Fan Maintenance and Replacement
- Appendix E: Replacing and Adding System Components
- Appendix F: Inverter Arc Detection and Interruption
Opening Conduit Knockouts
Thisstepmaybeperformedaftermountingtheinverter.
1. MovetheSafetySwitchandtheinverterON/OFFswitchtoOFF.
NOTE
When the Safety Switch is OFF (for example during maintenance) it may be locked to
prevent safety hazard:
1. Move the Safety Switch to the Lock position.
2. Insert the lock through the knob opening and lock.
2. LoosenthescrewsonthefrontcoveroftheSafetySwitch,asshownbelow:
Figure 12: Opening the Safety Switch cover
3. RemovetheSafetySwitchcover.
4. OpentheACandDCconduitknockouts:Theswitchhasknockoutslocatedatthebottom,
backandsidesoftheenclosure,eachwithtwosizes:¾''and1''.Openthenecessarypair
accordingtotheconduitsusedintheinstallation,takingcarenottointerferewithanyof
theinternalcomponents.AUnibitdrillmaybeused.
Figure 13: Safety Switch knockouts
Chapter 3: Installing the Inverter
SolarEdge-Installation Guide MAN-01-00002-4.0