P400 Installation
Table Of Contents
- SolarEdge Installation Guide - North America Version 4.0
- Disclaimers
- Support and Contact Information
- Contents
- HANDLING AND SAFETY INSTRUCTIONS
- IMPORTANT SAFETY INSTRUCTIONS
- Chapter 1: Introducing the SolarEdge Power Harvesting System
- Chapter 2: Installing the Power Optimizers
- Chapter 3: Installing the Inverter
- Chapter 4: Connecting the AC and the Strings to the Safety Switch
- Chapter 5: Commissioning the Installation
- Chapter 6: User Interface
- Chapter 7: Setting Up Communication
- Appendix A: Errors and Troubleshooting
- Appendix B: Technical Specifications
- Appendix C: Mechanical Specifications
- Appendix D: External Fan Maintenance and Replacement
- Appendix E: Replacing and Adding System Components
- Appendix F: Inverter Arc Detection and Interruption
Step 2: Connecting a PV Module to a Power
Optimizer
l ConnectthePlus(+)outputconnectorofthemoduletothePlus(+)inputconnectorof
thepoweroptimizer.
l ConnecttheMinus(-)outputconnectorofthemoduletotheMinus(-)inputconnector
ofthepoweroptimizer.
Figure 7: Power optimizer connectors
NOTE
Images are for illustration purposes only. Refer to the label on the product to identify the
plus and minus input and output connectors.
Step 3: Connecting Power Optimizers in Strings
Youcanconstructparallelstringsofunequallength,thatis,thenumberofpoweroptimizers
ineachstringdoesnothavetobethesame.Theminimumandmaximumstringlengthsare
specifiedinthepoweroptimizerdatasheets.RefertotheSolarEdgeSiteDesignerforstring
lengthverification.
NOTE
The total cable length of the string (including power optimizers’ cables) should not exceed
1000ft./300m from DC+ to DC- of the inverter. Use at least 11 AWG/ 4 mm² DC cables.