7 Commissioning
7.1 Commissioning battery
If there is only one battery installed, use the following steps to put it in operation:
1) Press and hold the panel button on the left side of the unit for about 4s, after
the indicator lights on, release the panel button.
2) Make sure that the Run light is on. If it stays off, do not use the battery and
contact CFE or your distributor.
3) Turn the inverter on, and wait for the start-up sequence to complete fully.
When there are two or more batteries connected with parallel mode, after the
charging cable and the data cable has been connected correctly, follow these steps
to put them in operation:
1) Check battery voltage level is above 48V
If battery voltage is under 48V contact your distributor or CFE after service
customer careline for help.
2) Press and
HOLD the panel button for about 4s, after four seconds the indicator
lights will turn on.
3) Release the panel button.
For all batteries, make sure that the Run light is on.
a. Make sure the maximum voltage different between batteries less than
2.0V.
b. If not, the installer should balance the battery voltage and then parallel
connect batteries together.
c. Set the DIP switches like part 6-3 Settings for CAN /485 bus pins.
4) Turn the inverter on, and wait for the start-up sequence to complete fully.
7.2 Shutting down battery
Shut down the battery only when the battery is no charge or discharge current
which could be seen in your smart phone with APP.
1) Press and hold the Panel Button about 8s, after a disconnect voice of relay
come can release it.
2) Make sure that every light on the battery is off.
8 Troubleshooting
1) Every fault is presented by a fault code. If the battery fault light is on, please