User's Manual Part 1

Table Of Contents
3EM21522AAAA Insta
ll
ation
Issue 1, March 2008 DTR-0200-SA-SIRIUS
3-11
3.10
POST-INSTALLATION INSPECTION/TEST
Post installation inspecting/testing is described below as phase one, two, and three
inspecting and/or testing. Phase one and two inspecting/testing is to satisfy the site
owner that the system conforms to the owner’s requirements. Phase three testing is
the Alcatel-Lucent SIRIUS field test performed after installation or major equipment
maintenance to ensure that the repeater is performing according to SIRIUS require-
ments. An inspection/test form template is provided at the end of this section. A field
test report form template is provided at the end of the
Turn-up and Testing section of
this manual.
3.10.1
Inspection/Test Phases
Post installation inspection/testing will normally consist of three phases involving
the site owner’s representative, Alcatel-Lucent’s representative, and SIRIUS
Radio’s representative. A written record of each phase will be made identifying the
specific inspections and/or test(s) accomplished and the satisfactory or unsatisfac-
tory result(s) of each. A copy of the results will be furnished to each participating
representative
.
3.10.1.1
Phase One Inspection/Testing
Phase one inspection/testing will be performed at the discretion of the site owner’s
representative. The purpose is to ensure that Alcatel-Lucent installed equipment
meets all requirements established by the site owner. The site owner’s representa-
tive
(s) in conjunction with the Alcatel-Lucent representative and the SIRIUS Radio
representative will be involved in the inspection/testing process. Deficiencies will be
identified, recorded, and presented to the Alcatel-Lucent representative for correction.
3.10.1.2
Phase Two Inspection/Testing
Phase two will only be required if there were discrepancies found during the phase
one inspection/testing. After correction of the discrepancies, the site owner’s repre-
sentative, Alcatel-Lucent’s representative, and SIRIUS Radio’s representative will
once again be involved in an inspection/test to ensure satisfactory correction.
Results
of the phase two inspection/testing will be recorded and signed by all representatives
and a copy distributed to each.
3.10.1.3
Phase Three Testing
Phase three testing consists of The Alcatel-Lucent representative in conjunction with
a SIRIUS Radio representative performing repeater system field testing to ensure
satisfactory system operation. Final test results will be recorded and signed by each
representative who in turn will receive a signed copy.
3.10.2
Repeater System Field Testing
Refer to
Section 4, Turn-Up and Testing
in this manual for the system field test proce-
dure and
Paragraph 3.11, Post Installation Inspection/Test Form
template.