Installation manual
Introduction
5
851--160115 / B
2.4 Installation procedures
The installation of the standard SD 570 / SE 570 Sonar systems
includes the following stages:
The installation of the standard SP 270 Sonar system includes the
following stages:
• Mounting the Installation Trunk
• Mounting the Hull Unit
• Mounting the Transceiver Unit
• Mounting the Sonar Control Unit
• Cabling
• Start-Up
• Final Test
Refer to the cable plan, the main interconnection diagrams and the
outline dimensions drawings of the units.
2.5 Equipment responsibility
Upon receipt of the equipment, the installation shipyard and/or
the dealer automatically becomes fully responsible for the
equipment unless otherwise is stated in the contract. This
responsibility covers the storage period before the installation, the
actual installation, commissioning, and the period between the
commissioning and the acceptance of t he equipment by the end
user (normally the owner of the vessel into which the equipment
is to be installed).
The guarantee period for the system (as specified in the contract)
begins as soon as acceptance documents have been signed, unless
other arrangements have been made in the contract.
2.6 Receipt, unpacking and storage
On receiving the equipment, the shipyard and/or the dealer
should ensure that the delivery is complete and inspect each
container for physical damage. If the inspection at receipt reveals
indication of crushing, dropping, immersion in water or any other
form of damage, the recipient should request a representative
from the carrier to be present during unpacking.
During unpacking, the equipment should be inspected for
physical damage, i.e. broken controls and indicators, dents,
scratches etc.
If damage to the equipment is discovered, the recipient should
notify the carrier and Simrad so that Simrad can arrange for
replacement or repair of the damaged equipment.