Unit installation
FS 70 Installation Instructions
974-24007001/4.1 29
4 FS 70 INSTALLATION INSTRUCTIONS
4.1 Installation procedure
The installation of the FS 70 Trawl Monitoring System involves the
following steps:
• Deciding on the locations in the wheel house for the surface units.
• Mounting the surface units and making the connections between the
FS 70 Processor, the display unit, the FS Power Supply/TTM
interface unit, and other optional equipment being installed.
• Assembling the trawl unit.
• Running up the system on the test cable to verify proper installation,
configuring the control unit, and performing initial system tests.
• Installing the cable winch, snatch block and trawl cable, and
connecting the winch slip-rings to the control unit.
• Mounting the trawl unit to the head rope and completing the final
system test.
• Mounting the catch sensors to the cod-end of the trawl and other PI
sensors.
4.2 Surface Unit Installation
4.2.1 Mounting of Units
If you have selected the FS Integrated Rack Mounted System, you
can install the cabinet up to 30 meters from the monitors. With a
KVM extender option you can install the cabinet up to 150 meters
away from the monitors. If not, you will have to follow the
procedure indicated below.
The display unit should be located in the wheel house in a place that
provides a good view of the screen and avoids direct sunlight if
possible. Depending on the monitor that was selected the unit may
be mounted on top or recessed into the bridge console. Simrad
supplied display units include the necessary mounting brackets.